Sunday, 24 March 2019

How does resource level and specifically, the Parallel method, resolve this issue and what is the general impact on the schedule. Explain the relationship between post leveling schedule and the rolled-up (baseline) budget.


A Project Plan is prepared, which is defined as a management summary document that describes the essentials of a project in terms of its objectives, justification and how the objectives are to be achieved. It describes how all of the major activities under each project management function are to be accomplished, including that of overall project control. The project plan will evolve through successive stages of the project life cycle. A Project Plan is developed once the Business Case and Project Charter have been defined.

Developing a good schedule for managing the execution of a project is paramount to good project management practice. The Critical Path Method of scheduling is currently the most popular technique employed by scheduling practitioners. Understanding how a schedule has been created, as well as the impacts of progress and disturbances,

The Critical Path Method
The Critical Path Method (CPM) is the backbone upon which the project execution plan is built. It provides a dynamic analysis of activity sequencing and progress reporting, the foundation for excellent progress and performance analysis, such as earned value management, as well as a tool for resource deployment and management.

The CPM is a relatively simple concept. It consists of linking the activities that make up the project execution in a logical, sequential manner such that the execution is both practical and generally as fast as possible. For example, "Pour Foundation" activity must follow after the "Excavate Foundation" activity. Barring some revolutionary new construction method, anything otherwise is just not practical. However, if the foundation is of a long physical nature, it may be possible to overlap the two activities by delaying the pouring some finite time behind the start of the excavation, rather than waiting for the completion of the total excavation before starting any pouring. The point of this is that the practicality of activity sequencing is limited only by the feasibility of the actual work.
The speed of execution limited by another factor: the availability of the required resources. By resources we mean the personnel, materials and equipment that is necessary to perform a particular activity. Resource assignment and levelling is the subject of the second part of this paper.
By tying all the activities into a logical, sequential network, the CPM calculation can then proceed to determine the earliest possible time activities can be accomplished and the latest possible time activities need to be accomplished in order to meet the project completion date. The primary restriction of any CPM is that the total project execution must fit between the start and finish dates of the project. As we will see later, the CPM also provides the means to fit a particular set of activities between some intermediate dates between the project start and finish.
Calculating the start of each activity is essential as that determines the latest finish for any predecessor activities. The backward pass applies these algorithms from right to left through the entire schedule network until all activities have a late finish and a late start date assigned.
The combined picture of the forward- and backward passes looks as shown in Exhibit 3. The dates in this illustration are ordinal dates to facilitate the review of the formulas. The early dates, which resulted from the forward pass, are shown on top of each activity bar and the late dates, which resulted from the backward pass, are shown below each bar.
Since no project required finish date was specified, the backward pass started the calculations from day 22 as the default project finish date. This date came from the forward pass calculation and is the last early finish date of all activities in the project.
A project manager, when you generate a budget when setting a baseline financial project plan, you can select any active budget financial plan type that's available for budget creation. However, some financial plan types (including the default financial plan type selected in the budget generation options of the project plan type) are unavailable for selection in the following circumstances:
·         If you already selected an approved cost or revenue budget financial plan type for creating a budget version, then no other approved budget financial plan types are available.
·         If you want to select a financial plan type with budgetary control enabled on it, then it is unavailable for selection in the following circumstances:
o    The project or template is not enabled for budgetary control.
o    The business unit is not enabled for budgetary control.
o    The project is a sponsored project, then only an award budget is expected to be enabled for budgetary controls.
o    A different budgetary control enabled financial plan type is already used.

No comments:

Post a Comment